Construction management Q&A
How do I track retention and practical completion by trade?
Short answer
- Add each trade as a subcontractor on the site, such as plumbing, electrical or roofing, and allocate them to the stages where they work, so every stage shows who is responsible for it.
- Read your own contract, whether a JBCC agreement, a letter of appointment or a verbal arrangement, and note the retention percentage and release conditions in your own file, since the contract and not the software defines them.
- Create a budget category for retention held back from each trade, and enter each payment and each held-back amount manually in rand, so the money still owed is visible next to what has been paid.
- When a trade reports practical completion, update the progress of their stage by hand and write a diary note with the date, the snag list outcome and who was on site.
- Release retention only after you have confirmed the amount against your own agreement, enter it as a new cost with a clear note, and cancel entries only with a stated reason.
Practical example
- Example: a main contractor on an office refurbishment in Sandton holds back ten per cent on a R240 000 electrical subcontract. The R24 000 sits in a retention category, so the owner and the contractor both see what is still pending.
- Example: a roofing subcontractor in Pretoria declares practical completion on a Friday. The diary records a short snag list and the roofing stage is moved by hand from 90 to 100 per cent after the re-inspection.
- Example: a builder in Durban pays a plumber R38 000 in two instalments. Each is entered as a separate dated cost, so the trade’s total is easy to check against the original quote.
Common mistakes
- Releasing retention from memory instead of checking the amount and conditions in the written agreement, then arguing about the difference weeks later.
- Lumping all trades into one “subcontractors” cost line, which hides which trade is over its allowance and which is still owed money.
- Treating the software as if it certifies completion, when the decision to accept practical completion rests with the people named in your contract.
How 4construct helps
- 4construct tracks subcontractors, stage allocations, budget lines and manually entered costs. It does not generate payment certificates, calculate retention for you or run any approval flow, so the contractual decisions and the arithmetic stay with you and your professionals. Used consistently, it simply gives you a dated trail of who was paid what, which helps when memories differ at final account stage.