How do I track job costs on a GMP contract in Seattle?
Short answer
- Create the project with the owner, the street address and the guaranteed maximum price entered as the declared budget, and set the currency to USD so every later figure reads the same way.
- Split the budget into lines by category, such as labor, materials, subcontractors and general conditions, so each line shows how much of the cap you have planned to spend there.
- Enter each cost by hand when the invoice or timecard is confirmed, with a date, a category and a short note, so the record matches the paperwork you will hand the owner.
- Remember that a confirmed cost cannot be edited. If a vendor bills you twice, cancel the wrong entry with a written reason and enter the correct amount as a fresh cost.
- Open the project report once a week and compare spending per category with the budget lines, so a line drifting toward the cap shows up while there is still time to act.
Practical example
- Example: a four-story wood-frame apartment building in Ballard has a GMP of $6,400,000. The superintendent sets lines of $2,100,000 for framing labor, $1,900,000 for materials and $1,600,000 for trades. In month three, framing labor is at $1,450,000, so the team reviews crew size before it becomes a problem.
- Example: a tenant improvement in South Lake Union is capped at $850,000. The project manager enters the electrician and the drywall sub as separate subcontractor lines, then logs each confirmed invoice against its line, which makes the weekly owner meeting a ten-minute conversation about numbers instead of a search for paper.
- Example: a duplicate lumber invoice of $18,200 is entered by mistake. The bookkeeper cancels the entry with the reason "duplicate of invoice already logged" and enters the real amount once, so the cost history shows what happened and why.
Common mistakes
- Treating the GMP as one big number. Without lines per category you only find out you are over the cap when the total is already gone, and by then the cost has been spent.
- Waiting until month end to enter costs. Invoices pile up, details are forgotten and the budget picture the owner sees is weeks behind what is happening on the street.
- Trying to rewrite a confirmed cost instead of cancelling it with a reason. The history is meant to stay intact, so plan to cancel and re-enter whenever a figure was wrong.
How 4construct helps
- In 4construct you keep the declared budget, the budget lines and the manually entered costs for each project in one place, and the reports break spending down by project and by category.
- The tool does not import invoices, send alerts when you near the cap, or calculate shared-savings splits, so those steps stay with your accounting system and your contract. Check the contract language with your attorney or accountant.