How do I record change order costs on an Atlanta job?
Short answer
- When the owner agrees to extra work, decide which existing category it belongs under, or create a new budget line named for the change so its cost stays visible on its own.
- Raise the declared budget on the project by hand if the signed change adds money, and record the new total in the project notes so the history is easy to follow.
- Enter each cost tied to the change as a separate cost with the date, the vendor and a note naming the change, rather than folding it into the general materials line.
- Write what happened in the daily log, including the crew, the quantities and the day the extra work began, because a good log makes later conversations about scope much easier.
- If a cost was entered under the wrong line, cancel it with a stated reason and enter it again under the correct one, since confirmed costs cannot be edited.
Practical example
- Example: on a medical office buildout in Buckhead, the owner asks for six extra exam-room outlets and a second data drop. The contractor opens a budget line named for the change at $9,500 and enters the electrician invoice of $8,700 when it arrives.
- Example: a custom home in Decatur needs an added retaining wall after the geotechnical visit. The superintendent raises the declared budget by $22,000, adds a line for the wall and logs the crew and the block quantities on the days they work.
- Example: a $3,100 tile credit is entered as a cost on the wrong floor. The bookkeeper cancels it with the reason "entered on level two instead of level one" and records it again, which keeps both the correction and the original visible.
Common mistakes
- Hiding extra work inside the original lines. When the final numbers arrive, nobody can tell whether the overrun was a scope change or ordinary waste, and the conversation gets harder.
- Adjusting the declared budget without a note. A silent change makes the project history confusing, so write down what was agreed and when it was signed.
- Assuming the software manages the approval itself. Here the budget and costs are entered by your team, so the written agreement must still be kept through your normal paperwork.