How do I log wet-weather delays on an Auckland build?
Short answer
- Open the day entry first thing and record the weather in the field provided, using plain words such as steady rain from 7 am, then update it if the afternoon changes the picture.
- List who actually turned up, including subcontractors, and note when they left. A gang that came for two hours and went home still belongs in the record.
- Describe the work that could not proceed, for example roof underlay, exterior plastering or a concrete pour, and put it in the blockage field with the reason so the delay is visible by day.
- Record any work that went ahead anyway, such as internal framing or fit-out, and the quantities completed, so the day shows what was done as well as what was lost.
- At the end of the month, review the diary for the stage and count blocked days. That gives you an evidence-based figure to take into a conversation about the programme.
Practical example
- Example: a two-storey house in Albany, Auckland, during a wet July. Of twenty-two working days, seven carry a blockage note for rain, and the diary lists the cladding crew as sent home on four of them.
- Example: a townhouse development in Mt Albert. The site manager records a concrete pour postponed on a Tuesday, lists the three people on site doing internal work instead, and notes 12 m3 of concrete moved to Thursday.
- Example: a deck and retaining wall in Titirangi. After a week of rain the owner asks why progress slowed, and the daily entries with weather, headcount and blockage notes answer the question in a few minutes.
Common mistakes
- Writing only bad weather as a blockage and ignoring the work that continued indoors. The diary then makes the site look idle when it was not.
- Using vague notes such as rain again. A clear time, task and crew size is what lets someone else understand the day later.
- Expecting the tool to fetch the forecast or flag a delay for you. Weather is typed in by you, and nothing is sent automatically.