Construction management Q&A
How do I prepare site records for a CCC application?
Short answer
- Create the site with the owner, street address, start and planned finish dates, and keep the building consent number in the site name or a document reference so every record points back to the same job.
- Write a diary entry each working day covering work done, who was on site, quantities placed and any blockage. A steady daily trail is easier to rely on than memories gathered at the end of the build.
- For each key paper, such as the consent drawings, inspection outcomes or a producer statement, add a document reference and attach the one PDF or photo you hold, up to 20 MB.
- When a licensed practitioner finishes their part, add a document reference for their record of building work as soon as you receive it, and note the stage it relates to.
- Before you apply, filter the diary by stage and check each stage has its entries and references. Gaps are far cheaper to chase while the crew is still on the job than months later.
Regulations and references
- The Building Act 2004 sets out the building consent and code compliance certificate process; applications go to the building consent authority, usually your territorial authority. Check current requirements with your council.
- MBIE publishes guidance at building.govt.nz on records of building work from licensed building practitioners. Confirm which records your particular consent needs with your council before you apply.
Practical example
- Example: a three-bedroom house in Hamilton with a NZ$480,000 declared budget. The builder logs a diary entry daily, adds thirty-odd document references over the build, and each inspection sheet is attached as a single PDF to its own reference.
- Example: a renovation in Dunedin where the owner changes mid-way. The diary shows who attended on which dates, and the stage list shows framing finished, so the incoming builder can see exactly where the work stopped.
- Example: a small commercial fit-out in Palmerston North. The project manager creates one reference per producer statement, adds the date received, and uses the stage filter to confirm nothing is missing before the owner applies.
Common mistakes
- Leaving diary entries until the end of the week, so the weather, headcount and quantities are guessed. Short daily entries are quicker and more believable.
- Attaching a bundle of scans as a single file. Each document reference holds one file, so scan and name them one by one.
- Assuming the software issues the certificate or checks compliance. It stores your references and records only; the decision stays with the council.
How 4construct helps
- 4construct keeps your site diary, stages and document references in one place, with one attached file per reference in PDF, JPG, PNG, WEBP or HEIC up to 20 MB.
- It does not manage document versions, sign or certify anything, or send alerts, and it does not submit consent applications. Treat it as a tidy record, not as a compliance check.