Construction management Q&A
How do I track winter frost delays on a Latvian site?
Short answer
- Record the weather in the daily journal every working day in the cold season: air temperature, snow or rain, and whether the planned work could proceed or had to stop.
- When work stops, enter the blocker as a clear reason, for example frost on the slab or snow on the roof, so lost days can be counted at the end of the winter.
- Add extra winter costs such as heating, tarpaulins, additives or hired heaters as separate manual cost lines in a dedicated budget category called winter measures.
- Mark the affected stage with an honest manual progress figure instead of keeping the old percentage, so the schedule you show others reflects the real state of the work.
- At the end of March compare lost days and winter spending across sites, and use the figures when you plan the next autumn and quote the next client.
Practical example
- Example: a contractor in Cēsis plans to pour a ground slab in January. Five working days are lost to hard frost. The journal lists the dates, and a cost line of EUR 1,200 records rented heaters and covers.
- Example: a roofing subcontractor in Liepāja cannot work for three days because of storm wind off the Baltic. The blocker entries show why the stage is at 40 percent instead of the planned 60 percent in February.
- Example: a builder in Valmiera sees that winter measures cost EUR 3,500 on a house with a EUR 180,000 budget, about two percent. The next client quotation for a January start includes that item openly.
Common mistakes
- Treating bad weather days as invisible. Without a written blocker, nobody can later prove that the delay came from frost or storm and not from poor planning.
- Mixing heating and protection costs into general materials, so the true price of winter work cannot be separated when the next season is planned.
- Leaving the stage progress unchanged during a freeze, which hides the delay until the client or owner asks why the handover date slipped.
How 4construct helps
- 4construct records weather and blockers in the daily journal, lets you enter winter costs manually under their own budget category, and lets you set stage progress by hand.
- It does not pull weather forecasts, send frost alerts or calculate concrete curing times. You enter the facts, and the reports compare them per site and per category.