Construction management Q&A
How do I run a site diary next to the Latvian build log?
Short answer
- Treat the official construction log (būvdarbu žurnāls) in BIS as the record for the authorities, and the daily site journal as your own working memory about people, quantities, weather and blockers.
- Decide who writes the daily journal entry: usually the foreman (meistars) or site manager (būvdarbu vadītājs), at the end of every working day, while the details are still fresh in their head.
- In each journal entry note the work done, the crews present, quantities such as m³ of concrete or m² of formwork, the weather, and anything that stopped work that day.
- Once a week, compare your journal against the BIS log and fix gaps, so that what the supervisor (būvuzraugs) sees matches what really happened on the plot.
- Keep the journal per site, never mixed across projects, so a dispute about a delay in Jelgava does not require digging through notes from a job in Ventspils.
Regulations and references
- In Latvia the construction log (būvdarbu žurnāls) is kept in the Building Information System (BIS) under the General Building Regulations (Cabinet Regulation No. 500). Check the current text on likumi.lv or with the Building State Control Bureau (BVKB).
Practical example
- Example: a contractor builds a two-storey house in Mārupe. The BIS log shows that foundations were completed in week 9. The daily journal adds that two days were lost because the pump truck arrived late and that 18 m³ of concrete was poured.
- Example: a foreman in Sigulda records, every evening, six crew members, 40 m² of wall blocks laid, light snow and a delivery of insulation delayed until the next morning. Three weeks later this note explains a schedule slip to the owner.
- Example: a manager responsible for three houses in Ādaži keeps one journal per address, so each entry about weather, crews and blockers belongs to exactly one site and one budget in EUR.
Common mistakes
- Believing the official log replaces the daily journal. The log serves the authorities; it rarely holds crew numbers, small blockers or the day-to-day reasons for a delay.
- Writing journal entries a week later from memory. Quantities and weather become guesses, and the entry loses value in any later discussion with the client or a subcontractor.
- Keeping one shared notebook for several plots, which makes it impossible to say which delay belongs to which project when you settle accounts.
How 4construct helps
- 4construct gives every site a daily journal with work done, crew, quantities, weather and blockers, kept next to the budget and stages of the same site.
- It does not connect to BIS and does not replace the official construction log, so continue to complete the log as the regulations require. It also does not send automatic reminders.