Construction management Q&A
How do I compare several sites in Riga and Liepāja?
Short answer
- Use the same budget categories on every site, for example materials, labour, subcontractors, machinery and reserve, because only identical categories make sites comparable in a report.
- Set the currency explicitly per site. In Latvia that is EUR for nearly all work, but a project with foreign suppliers can use another one, and the report must not mix them silently.
- Update manual stage progress and enter confirmed costs on a fixed weekly day, for example Thursday, so that the numbers you compare are from the same moment.
- Open the reports per site and per category, then ask the same questions on each site: which category is over plan, which stage is behind, which blockers keep coming back.
- Use the comparison to move people and money. A crew that is idle in Liepāja may be needed in Rīga, and a site that always runs over in transport needs a better plan.
Practical example
- Example: a firm runs a EUR 300,000 office fit-out in Rīga, a EUR 150,000 warehouse in Liepāja and a EUR 90,000 house in Jūrmala. The Thursday review shows only Liepāja over budget in transport.
- Example: two sites use the same eight categories. The reports reveal that machinery hire is 18 percent of spending in Liepāja and only 7 percent in Rīga, which prompts a question about idle equipment.
- Example: a manager sees that two stages in Daugavpils are behind while Jelgava is ahead. The foreman team is split for two weeks, and the journal records the reason for the move.
Common mistakes
- Inventing different categories for each site, which makes the reports look detailed but impossible to compare when you want to learn something about the company as a whole.
- Comparing numbers entered on different days, so one site looks late and another early simply because someone updated costs three weeks ago.
- Looking only at the total of a site. A project can be on budget overall while one category, such as subcontractors, is far over and others hide the problem.
How 4construct helps
- 4construct provides reports by site and by category, based on the budgets, costs and stage progress you enter. What the reports show depends on the plan you use.
- It does not export reports, send automatic alerts or monitor sites in real time. You review the reports yourself, on the day you choose, and decide what to do next.