How do I assign subcontractors across several Riga sites?
Short answer
- Create one record for every subcontractor (apakšuzņēmējs) or crew you use, including the specialty such as electricians, plasterers, roofers or groundworks, and the contact person.
- For each site and stage, allocate the subcontractor who is responsible, for example the plastering crew on stage three of a house in Pārdaugava, so that nobody is unclear about who owns a task.
- When a crew moves from one site to another, update the allocation on both sites the same day, otherwise two managers will think they can count on the same people on the same morning.
- Record the subcontractor in the daily journal entries, with the crew size and quantities done, so you can later justify payments to them with your own notes about the work.
- Review allocations every Friday for the following week and spot overlaps, for example the same electrician planned in Imanta and Ķekava on the same Monday.
Practical example
- Example: a general contractor runs sites in Imanta, Mežaparks and Ķekava. The electrical crew is allocated to stage four in Imanta and stage two in Mežaparks, and the Friday review shows the overlap before it becomes a missed day.
- Example: a plastering firm from Jūrmala works on two houses. Its allocation lists the weeks on each stage, and the journal shows crew size, so a EUR 4,000 stage payment can be matched to the days really worked.
- Example: a site manager replaces a roofing crew on a Sigulda house. The old allocation is removed and the new company is added to the same stage, leaving a clear trail of who was responsible and when.
Common mistakes
- Keeping the list of subcontractors only in a phone address book, so a colleague taking over the site cannot tell who is responsible for which stage.
- Allocating a crew to a whole site rather than to stages, which makes it impossible to see when their part of the work should actually begin and end.
- Forgetting to remove a crew from a site after they leave, so reports keep showing them as responsible for work that someone else finished.
How 4construct helps
- 4construct stores subcontractors and their allocations per site and per stage, and links them to the daily journal and to manual cost lines.
- It does not run an approval flow, send notifications to subcontractors or check their licences. Verifying registrations and insurance stays a manual task for you.