How do I file photos of covered works (segtie darbi)?
Short answer
- Make a short list of elements that will be hidden by later work, such as reinforcement before a pour, insulation under a screed, pipes in trenches and the roof structure before cladding.
- Before closing each element, photograph it clearly with a note of date, place and what is visible, because once the cover is on nobody can check it without breaking it open.
- Create one document reference per element on the site and attach one file, in PDF, JPG, PNG, WEBP or HEIC format, up to 20 MB, with a title that names the element and the stage.
- If several photos belong to the same element, merge them into one sheet or PDF first, or create separate references, since each document reference carries exactly one file.
- Mention the same element in the daily journal, so that the date, the crew and the weather can be found beside the picture when somebody asks questions months later.
Regulations and references
- Latvian building regulations require that covered works are recorded and accepted in the Building Information System (BIS) before work continues. Check the exact current wording with the Building State Control Bureau (BVKB) or a specialist.
Practical example
- Example: before a slab pour in Ogre, the foreman photographs the reinforcement mesh with a tape measure. The PDF is attached to a reference named reinforcement, slab, stage 2, and the journal notes 12 m³ of concrete.
- Example: a plumber in Rīga closes a trench with drainage pipes. A single HEIC photo from a phone, 4 MB, is saved under the stage trench and drainage, and the entry is easy to find a year later when the owner calls.
- Example: a roofing crew in Ventspils compiles six photos of the roof structure into one PDF of 9 MB, then attaches it to one reference, which keeps the attachment within the 20 MB limit.
Common mistakes
- Photographing only after the screed or cladding is installed, when the important layer is no longer visible and the picture proves nothing about what is underneath.
- Saving photos with names such as IMG_4021 on one phone, so that nobody else on the team can find the right photo when the supervisor or client asks for it.
- Expecting document versions or signatures inside the system, when each reference is a simple record with a single attached file that you must manage yourself.
How 4construct helps
- 4construct stores document references per site, each with one attached file, so photos and scans of hidden works are easy to find beside the stage and the journal entry.
- It does not manage versions, collect signatures, certify acceptance or replace the BIS procedure. Follow the official process in BIS and use 4construct as your own organised archive.