How do I track real costs on a fixed-price contract?
Short answer
- On a fixed-price (vienotas cenas) contract with a client, write the agreed total into the site as the declared budget in EUR, because every later decision is measured against that number.
- Divide that total into categories that match how you actually spend: materials, own labour, subcontractors, machinery hire, transport and a small reserve for surprises.
- Enter each cost manually when it is confirmed, never in a lump at month end, and give it the right category so that one invoice does not blur the picture of the whole site.
- Check the confirmed total against the contract sum at every stage change. If you already spent seventy percent while only half of the work is finished, stop and talk before continuing.
- If the client requests changes, record the extra work as its own budget line, with a note of what was agreed, so that a variation does not silently eat the margin.
Practical example
- Example: a contractor agrees to build a garage and workshop in Kuldīga for EUR 95,000. After the walls, the subcontractor category is at EUR 18,000 against EUR 15,000 planned, a gap that is visible immediately.
- Example: at the half-way point of a house in Saulkrasti the site is 50 percent complete by manual progress, but confirmed costs are already EUR 78,000 of a EUR 120,000 contract, so the manager renegotiates a change order.
- Example: a client asks for a larger terrace on a house in Tukums. The builder adds a EUR 6,000 line with a note, and the extra spending is separated from the original contract sum.
Common mistakes
- Judging profit only at the very end of the job, when nothing can be corrected any more and the whole margin has already been spent on the site.
- Mixing costs of two sites in one entry because the supplier delivered on the same truck, which makes both budgets unreliable and hard to reconcile.
- Accepting small extras verbally without recording them, so that the client remembers a free favour and the contractor remembers a cost that nobody can document.