Construction management Q&A
How do I plan concrete pours in an Icelandic winter?
Short answer
- Split the structural work into small stages, such as footings, wall pour one, wall pour two and slab, so that a weather delay moves one stage and not the whole project.
- Record the weather in the daily log every working day: temperature, wind and precipitation. After a few weeks you have your own record of how often pours were really possible on that site.
- When a pour is postponed, write it as a blocker with the reason, for example strong wind for the crane or frost on the formwork, and the date you expect to try again.
- Add the extra winter costs as separate cost entries, such as heating, tarpaulins or extra hours, and put them under their own budget category so they do not hide in general costs.
- Set the stage progress by hand after each pour, based on what stands on site. Do not let a planned figure remain once the weather has changed the real situation. Review the log each Friday with the foreman, so the plan for the coming week is based on what the weather really allowed in the week that has just ended.
Practical example
- Example: a house in Akureyri has a wall pour planned for a Tuesday in November. The forecast shows frost and 15 metres per second wind, so the site manager logs a blocker and moves the stage by four days without touching the rest of the plan.
- Example: in Reykjavík a small crew works in under six hours of daylight in December. The log shows 24 working hours in the week instead of 40, and the site manager uses that figure when promising a date to the owner.
- Example: a contractor in Ísafjörður budgets 600,000 ISK for winter heating and covers. It is a separate category, so after the season the owner can see exactly what the weather cost.
Common mistakes
- Planning the schedule from a calendar designed for continental climates. Icelandic wind, rain and short days make several pours per week unrealistic in winter on many sites.
- Not writing down the weather. When the owner asks why a stage took eleven weeks, memory is a weak argument compared with a dated log.
- Absorbing winter costs into materials or labour. Later it is impossible to say whether the budget failed because of prices or because of the season.
How 4construct helps
- 4construct records weather in the daily log, lets you mark blockers, and tracks stage progress and costs that you enter yourself. It does not predict weather, send storm warnings, or check concrete curing or temperature requirements for you.