Construction management Q&A
How to record phase inspections in an Icelandic site log?
Short answer
- Break the building into stages that match the points where an inspection (áfangaúttekt) is usually needed: foundation, slab, frame, roof and weather-tightness, installations, and finishing.
- On the day of an inspection, write a daily-log entry that names the stage, the people on site, the work done and any quantities, so the entry stands on its own months later.
- Record every remark from the inspector as a blocker in the log, with a short description of what has to be fixed before the work can go on to the next part.
- When the fix is done, add a new entry for the day, describing what changed and who did it. The log now shows the full cycle from remark to correction, in dated order.
- Update the stage progress by hand only when the inspection is passed. Progress in 4construct is set manually, so it should reflect the real situation, not the plan.
Regulations and references
- The City of Reykjavík states that phase inspections are part of the byggingarstjóri’s internal inspection, that results are recorded in the Mannvirkjaskrá of HMS, and that remarks must be corrected and the inspection repeated. Check the current procedure with your byggingarfulltrúi.
- Approved design documents for each work item are expected on site before the work begins, according to the same guidance. Verify the exact requirement with the authority.
Practical example
- Example: a detached house in Garðabær reaches the stage of a closed roof. The site manager logs the date, a crew of six, the weather (rain, 4 degrees) and a blocker: one flashing detail at the chimney must be redone before the inspection.
- Example: a warehouse in Reykjanesbær has its slab inspected. The log entry lists 180 square metres poured, the concrete supplier, and the inspector’s one remark about a cover layer, which is repeated in a second entry three days later.
- Example: a summer house near Hella is built over two seasons. Because each inspection has a dated entry, the owner can open the site in spring and see exactly where the last season ended.
Common mistakes
- Writing the inspection result only on a paper form, so the log and the stage progress say nothing about it. Whoever takes over the site cannot reconstruct what was approved.
- Marking a stage as complete before the remarks are fixed. The progress figure then looks better than reality, and the next trade starts on top of unfinished work.
- Using vague entries such as “work continued”. An entry without date, team, quantities and blockers is of little use as evidence of what happened on that day.