How do I track costs on an ÍST 30 contract?
Short answer
- Read the contract sum and the main parts of the tender (útboð) first, then turn them into budget lines in 4construct, for example groundwork, concrete, framing, roofing, installations and finishing.
- Declare the budget for the site in ISK. Each site carries its own currency, so a project priced in ISK stays in ISK, even if one invoice arrives in euros.
- Enter each cost by hand when you have the invoice or the agreed amount, and pick the budget category it belongs to. Confirm the entry once you are sure about it.
- Confirmed costs cannot be edited afterwards. If a mistake is found, cancel the entry and state the reason, then enter the correct cost, which leaves a clean trail for the final account.
- Compare spend against each budget line in the reports before every payment round, and write down in the site log why any line is moving faster than the stage progress.
Regulations and references
- ÍST 30:2012, “Almennir útboðs- og samningsskilmálar um verkframkvæmdir”, is referenced in Icelandic public tender documents, for example from Vegagerðin. The standard text is published through Staðlaráð Íslands; read the clauses that apply to your contract directly.
Practical example
- Example: a municipal school extension in Akranes is tendered for 240 million ISK. The contractor splits the budget into eight lines and enters the first concrete invoices of 18 million ISK against the foundation line.
- Example: a subcontractor invoice for roofing is entered twice by mistake. The site manager cancels the duplicate with the reason “duplicate invoice”, and the confirmed original stays untouched in the history.
- Example: on a 90 million ISK industrial hall in Hafnarfjörður, the reports show that the installations line has used 70 percent of its budget while the stage is at 40 percent. This is a prompt for a conversation with the subcontractor.
Common mistakes
- Mixing the contract sum with the internal budget. The contract sum is what you are paid; the budget lines are what you expect to spend. Keep them separate or margins disappear.
- Entering costs only at the end of the month. The report is then always late, and decisions about orders and crews are made on old numbers.
- Deleting a wrong cost in a spreadsheet instead of cancelling it with a reason. Later it is impossible to explain why the final figure differs from the invoices.
How 4construct helps
- 4construct holds budget lines per category, manually entered costs with a clear confirmed or cancelled status, and reports per site and category depending on the plan. It does not read your contract, generate payment applications, import invoices or calculate taxes.