Aukaverk-breytingar-kostnadur-afturkalla

Construction management Q&A

How do I record extra work (aukaverk) on a site?

Short answer

  1. When the owner asks for a change, write it down the same day in the daily log: what is changed, who asked for it, and which stage it touches.
  2. Add a separate budget category for extra work, so that the original budget lines remain readable and the owner can see what the changes cost on top.
  3. Enter the cost of the extra work by hand when it is agreed or invoiced, choose the extra-work category and confirm it only when the amount is right.
  4. If an entry turns out to be wrong, cancel it and state the reason. A confirmed cost cannot be edited, so the history keeps both the mistake and the correction.
  5. Before the final account, read the report by category and go through the extra-work lines with the owner, using the log entries to explain each one. Ask the owner to confirm the total of the extra-work category in writing at that meeting, so that the final account starts from a figure both sides have already seen.

Practical example

  • Example: the owner of a house in Hveragerði decides to add a sauna room. The site manager logs the request, adds a category “Extra work” and enters 1.8 million ISK for framing and insulation once the price is agreed.
  • Example: an extra wall in a commercial space in Reykjavík is entered at 420,000 ISK by mistake instead of 240,000. The entry is cancelled with the reason “digits swapped” and the correct cost is added.
  • Example: at the end of a project in Selfoss, the owner questions four extra-work lines. The site manager opens the log entries behind them, and each one has a date, a name and a reason.

Common mistakes

  • Agreeing to changes only by phone and writing them down weeks later. By then, nobody remembers whether the price was a total or a rate, or who approved it.
  • Hiding extra work inside the original budget lines. The owner then thinks the base price was too low, when in fact the scope grew.
  • Cancelling a cost without a reason, or avoiding the cancellation function by editing numbers elsewhere. The honest history is the best protection in a dispute.

How 4construct helps

  • 4construct lets you log changes, enter costs by hand under their own category, and cancel confirmed entries with a stated reason. It does not run an approval flow, produce variation orders or send them to the owner, and it does not calculate taxes.
4b2b.net
Business Ecosystem
4conta.ro
Accounting
4invoices.net
Invoicing App
4expenses.net
Expense Management
4notify.net
Notifications
4hosting.net
Hosting
4database.net
Databases
4buildsite.net
Website Builder
4myapp.net
App Builder
4avatars.net
AI Avatars
4chaty.net
AI Chatbot
4webagency.net
Web Agency Software
4softedu.net
Education Websites
4softcrm.net
CRM Platform
4softerp.net
ERP System
4softhr.net
HR Management
4mystaff.net
Staff Portal
4construct.net
Construction Companies
4mycontracts.net
Contracts
4docs.net
Document Management
4appointments.net
Appointments
4marketingonline.net
Marketing
4insurance.net
Insurance
4property.net
Real Estate
4lawyers.net
Legal Software
4mygarage.net
Auto Service
4driving.net
Driving Schools
4fleet.net
Fleet Management
4myevents.net
Events
4therapy.net
Therapy
4clinics.net
Clinics
4dental.net
Dental Practices
4restaurants.net
Restaurants
4beautify.net
Beauty Salon
4gym.net
Fitness Gyms
4guards.net
Security Companies
4softvet.net
Veterinary Clinics
4softauto.net
Automotive Business Software
4marketplace.net
Marketplace
4shopy.net
Online Store
4pricing.net
Price Comparison
4salefood.net
Food Delivery
4rentify.net
Rentals
4transports.net
Transport
4agencytravel.net
Travel Agency
4hotel.net
Hotel Management
4ong.net
NGO Management