Construction management Q&A
How do I record extra work (aukaverk) on a site?
Short answer
- When the owner asks for a change, write it down the same day in the daily log: what is changed, who asked for it, and which stage it touches.
- Add a separate budget category for extra work, so that the original budget lines remain readable and the owner can see what the changes cost on top.
- Enter the cost of the extra work by hand when it is agreed or invoiced, choose the extra-work category and confirm it only when the amount is right.
- If an entry turns out to be wrong, cancel it and state the reason. A confirmed cost cannot be edited, so the history keeps both the mistake and the correction.
- Before the final account, read the report by category and go through the extra-work lines with the owner, using the log entries to explain each one. Ask the owner to confirm the total of the extra-work category in writing at that meeting, so that the final account starts from a figure both sides have already seen.
Practical example
- Example: the owner of a house in Hveragerði decides to add a sauna room. The site manager logs the request, adds a category “Extra work” and enters 1.8 million ISK for framing and insulation once the price is agreed.
- Example: an extra wall in a commercial space in Reykjavík is entered at 420,000 ISK by mistake instead of 240,000. The entry is cancelled with the reason “digits swapped” and the correct cost is added.
- Example: at the end of a project in Selfoss, the owner questions four extra-work lines. The site manager opens the log entries behind them, and each one has a date, a name and a reason.
Common mistakes
- Agreeing to changes only by phone and writing them down weeks later. By then, nobody remembers whether the price was a total or a rate, or who approved it.
- Hiding extra work inside the original budget lines. The owner then thinks the base price was too low, when in fact the scope grew.
- Cancelling a cost without a reason, or avoiding the cancellation function by editing numbers elsewhere. The honest history is the best protection in a dispute.