Construction management Q&A
How do I manage delays from imported building materials?
Short answer
- At the start of the project, mark the stages that depend on imported items, such as windows, steel, insulation or technical equipment, because they arrive by ship or air and may take weeks.
- When a delivery date slips, write a blocker in the daily log with the item, the supplier and the new expected date, so that everyone reads the same explanation.
- Change the stage and allocations only for the work that is truly blocked. Move crews to other stages on the same site, or to another site, instead of paying for idle time.
- Enter the extra costs of the delay by hand, such as storage, express freight or a second visit by the subcontractor, under a separate category so the cause remains visible.
- At the end of each week, read the log and the budget report together, and tell the owner honestly which stages have moved and by how much. A short written note to the owner each Friday, based on the log, is usually enough to keep trust high, even when the news about the delivery date is not good.
Practical example
- Example: windows for a house in Mosfellsbær are ordered from abroad and the shipment is delayed by three weeks. The site manager logs the blocker and moves the crew to interior framing, so only the glazing stage is late.
- Example: a contractor in Reykjavík pays 350,000 ISK for air freight on a missing steel connector. It is entered as a cost under “delay” instead of materials, and later the owner understands the increase.
- Example: a bad storm stops the ferry to Vestmannaeyjar for several days. The log shows four days without deliveries, and the subcontractor’s allocation is shifted to the next stage on the island.
Common mistakes
- Ordering imported items only when the stage starts. On an island, lead times are the real critical path, and the crew arrives to find nothing to install.
- Letting the whole schedule slide because one delivery slipped. A good site plan can almost always move other work forward while waiting.
- Paying express freight without recording why. Later the owner questions the invoice and nobody remembers what the situation was. A one-line note in the log on the day of the decision is enough.