How do I report on several sites in Greater Reykjavík?
Short answer
- Create one site per project, whether it is a block in Kópavogur, a terrace in Hafnarfjörður or a renovation in Reykjavík, each with its own client, address, dates and ISK budget.
- Use the same stage structure and the same budget categories on every site where possible. A consistent structure makes the comparison between projects fair and quick.
- Ask the foremen to write the daily log on each site, even briefly. A report is only as good as the log and the costs that stand behind it.
- At the end of each month, open the report by site and by category and compare spend against budget and stage progress. Note the two or three sites that need attention first. Write down which category or stage looks different from the others and who will check it this week.
- Share the main findings with the owners or the management in your own meeting. The report supports the conversation; the decisions about crews and orders remain yours. Keep a short written note of what was agreed, and look at the same report again next month to see whether the sites that needed attention have really improved.
Practical example
- Example: a developer runs three sites at once, in Kópavogur, Garðabær and Reykjavík, with budgets of 480, 210 and 95 million ISK. The monthly report shows the Garðabær site is at 55 percent of budget but only 40 percent of progress.
- Example: a mid-sized contractor in the capital area compares the installation category across all sites at the end of the month. One site spends much more than the others, which leads to a check of subcontractor invoices before the next payment.
- Example: a small renovation firm has six short projects in different municipalities. A separate site for each keeps the owners’ budgets from mixing and makes the final account easy to prepare.
Common mistakes
- Combining several projects into one site to save time. The budget, the log and the final account then become impossible to separate.
- Using different categories on each site. The report cannot compare them, and the work of summarizing is moved back into spreadsheets.
- Reading only the budget total. A site can be under budget simply because work has not been done yet; always check it against stage progress.