Construction management Q&A

How do I control materials on site so they don't go missing?

Short answer

  1. Receive every delivery on site and record the quantity actually unloaded, not the quantity ordered.
  2. Photograph the delivery and attach the photo to that day in the site journal.
  3. Allocate consumption to the stage the material was used on, not to the site in general.
  4. Periodically compare recorded consumption against the bill of quantities, on the expensive items.
  5. Investigate any gap larger than normal wastage while the crew is still on site.

What the law says (brief)

  • Order 2634/2015 on financial and accounting documents — material receipts are evidenced by a delivery note or goods received note, and consumption by a material issue note.
  • Accounting Law 82/1991 — material stocks are managed against documents and verified by stocktaking.
  • Regulation (EU) No 305/2011 on construction products — materials incorporated into the works must carry a declaration of performance and CE marking, and their paperwork belongs in the construction technical logbook.
  • Law 10/1995 on construction quality — using products without conformity documents leaves the contractor liable, regardless of who bought the material.

Practical examples

  • Example: on a 12-apartment site the bill of quantities allows 1,290 m² of floor tiles plus 5% wastage, i.e. 1,355 m². Recorded consumption reaches 1,520 m². The 165 m² gap, at 70 RON/m², is 11,550 RON that never made it into the building.
  • Example: a 24 t cement order is unloaded as 22.4 t weighed at the gate. Recorded that day, with a photo of the weighbridge ticket, the shortfall is settled with the supplier that month rather than at year-end stocktaking.

Common mistakes

  • Signing for the material against the ordered quantity, without checking what was actually unloaded.
  • Not allocating consumption to stages, so you can never say which piece of work overconsumed.
  • Comparing consumption with the bill of quantities only at the end, when there is nobody left to ask.
  • Leaving expensive materials — copper, tiles, joinery — without a daily record, on the assumption it will show up at the end anyway.

How 4construct helps

  • Deliveries and consumption are logged in the daily journal, straight from site, with photos attached to the day.
  • Material consumption feeds the project's materials cost centre automatically.
  • The overrun alert on the materials cost centre fires during execution, not at final account.
  • Consumption is visible per stage, so discrepancies surface at the stage that caused them.
4b2b.net
Business Ecosystem
4conta.ro
Accounting
4invoices.net
Invoicing App
4expenses.net
Expense Management
4notify.net
Notifications
4hosting.net
Hosting
4database.net
Databases
4buildsite.net
Website Builder
4myapp.net
App Builder
4avatars.net
AI Avatars
4chaty.net
AI Chatbot
4webagency.net
Web Agency Software
4softedu.net
Education Websites
4softcrm.net
CRM Platform
4softerp.net
ERP System
4softhr.net
HR Management
4mystaff.net
Staff Portal
4construct.net
Construction Companies
4mycontracts.net
Contracts
4docs.net
Document Management
4appointments.net
Appointments
4marketingonline.net
Marketing
4insurance.net
Insurance
4property.net
Real Estate
4lawyers.net
Legal Software
4mygarage.net
Auto Service
4driving.net
Driving Schools
4fleet.net
Fleet Management
4myevents.net
Events
4therapy.net
Therapy
4clinics.net
Clinics
4dental.net
Dental Practices
4restaurants.net
Restaurants
4beautify.net
Beauty Salon
4gym.net
Fitness Gyms
4guards.net
Security Companies
4softvet.net
Veterinary Clinics
4softauto.net
Automotive Business Software
4marketplace.net
Marketplace
4shopy.net
Online Store
4pricing.net
Price Comparison
4salefood.net
Food Delivery
4rentify.net
Rentals
4transports.net
Transport
4agencytravel.net
Travel Agency
4hotel.net
Hotel Management
4ong.net
NGO Management