Construction management Q&A
How do I work out the real cost per square metre of a build?
Short answer
- Fix your reference area and use it consistently — usually the total built floor area.
- Add up actual costs across the four cost centres: labour, materials, subcontractors, equipment.
- Add site overheads: site setup, utilities, transport, fees and permits.
- Divide total cost by the reference area — the result is the real cost, not the quoted one.
- Compare it with the original estimate, cost centre by cost centre, to see where the gap comes from.
What the law says (brief)
- Government Decision 907/2016 on the stages of technical and economic documentation — for publicly funded projects the general cost-estimate structure is the reference framework, and many private firms use it as their cost-breakdown model.
- Accounting Law 82/1991 — every cost must be supported by a document: invoice, work statement, material issue note, payroll sheet.
- Fiscal Code, Art. 281(7) — the moment the work counts as performed, on issuing or accepting the work statement, also sets the period the cost falls into.
- Note: cost per square metre has no single legal definition. Without a stated reference area, two figures are not comparable.
Practical examples
- Example: a house with 160 m² of total built floor area runs up actual costs of 512,000 RON — labour 148,000, materials 226,000, subcontractors 108,000, equipment 30,000. The real cost is 3,200 RON/m² against 2,950 RON/m² estimated, and almost all of the 250 RON/m² gap sits in materials.
- Example: on an 800 m² warehouse, dividing cost by usable area (760 m²) instead of total built floor area inflates cost per square metre by over 5%. That is why the basis is always stated.
Common mistakes
- Comparing costs per square metre that were calculated on different reference areas.
- Leaving out site overheads — setup, utilities, transport — and producing a cost that never happened.
- Calculating the cost only once, at the end; until then there is nothing to correct.
- Rolling client-requested extra works into the figure without separating them from the original budget.
How 4construct helps
- Costs accumulate in real time across the four cost centres, from confirmed work statements and expenses.
- The reference area is set on the project, so cost per square metre is recalculated with every new cost.
- Budget vs. actual per cost centre shows exactly where the variance comes from.
- The history of closed projects becomes the pricing baseline for the next similar job.