Construction management Q&A
How do I allocate trade subcontractors across stages?
Short answer
- Add every trade you use as a subcontractor, such as concrete, framing, HVAC, plumbing and electrical, with contact details, so that your list stays the same across all your sites.
- On each site, create the stages in build order, then allocate the subcontractors to the stages where they will actually work, which shows who is responsible for what at a glance.
- Record in the daily diary which crews were on site and how many people came, because the diary is where reality is written down and compared with the plan later.
- When a trade is late or leaves a stage open, note the blocker with the stage name, so the next trade waiting behind it is documented as delayed rather than at fault.
- Look at costs per subcontractor in the category reports and compare them with the budget line that was allocated for that trade before you approve the next payment.
Practical example
- Example: a custom home in Oakville has five trades. The contractor allocates concrete to the foundation, the framer to framing and roofing, and the electrician to rough-in, so each stage shows exactly one responsible company.
- Example: a duplex in Saskatoon sees the plumber arrive before framing inspection. The diary records the blocker and the contractor reassigns the plumber to the next stage until the framer finishes.
- Example: a contractor in Winnipeg splits a four-unit building into floors as stages. Each floor has the framer, plumber and electrician allocated in sequence, and the diary shows which trade was waiting on which, making it simple to resequence the next building.
Common mistakes
- Allocating a subcontractor to the whole site instead of to the stages where they work, so reports cannot tell which phase generated the cost.
- Forgetting to note short crews. A day with two people instead of six is the kind of detail that explains delays later.
- Assuming 4construct pays or approves subcontractors. It records allocations and costs, and payments remain outside the software.
How 4construct helps
- 4construct keeps a subcontractor list, allocates subcontractors to sites and stages, and links costs and diary entries to them.
- It does not run bidding, contracts, approvals, or automatic alerts, and it does not track equipment. You still agree terms and payments with each trade yourself.
- Reviewing allocations at the start of each stage takes a few minutes and avoids the common problem of a crew arriving at a stage nobody had told them was ready. Revisit the allocation list whenever a trade is replaced mid-project, so that costs and diary entries after the change are linked to the right company from that date forward.