How do I record building permit inspections on site?
Short answer
- Create the site with the permit holder as owner and the municipal address, then add one stage for each inspection milestone listed on your permit card, such as footings, framing and insulation.
- On the day an inspector visits, add a diary entry that says who attended, which stage was inspected, whether the work passed, and any deficiencies noted for correction.
- Add a document reference for the inspection report or permit card and attach one file to it, a PDF or phone photo up to 20 MB, so the paper sits next to the site record.
- If work cannot proceed because an inspection is pending or failed, record it as a blocker in the diary and name the subcontractor whose work must be corrected.
- Update the stage progress by hand only after the correction is done, so the percentage reflects what the inspector has actually seen.
Regulations and references
- In Ontario, building permits are issued under the Building Code Act, 1992 and the Ontario Building Code, and municipalities set out the inspection stages on the permit. Check notice periods with your local building department.
Practical example
- Example: a builder constructing a laneway house in Toronto records the footing inspection on a Tuesday, attaches a photo of the signed inspection card as a document, and marks the foundation stage at 100 percent.
- Example: in Barrie, a rough framing inspection fails because of a missing fire block. The diary notes the blocker, the framing subcontractor corrects it two days later, and the follow-up entry records the pass.
- Example: a builder in Kitchener schedules an insulation inspection before drywall. The diary entry the next morning records the pass, the inspector name, and the date drywall started, so the owner can see why interior finishing began on that particular day.
Common mistakes
- Covering up work before the inspection happens and then having to open it again, with no diary note to explain the lost days to the owner.
- Keeping inspection cards in a truck glovebox instead of attaching them to a document reference on the right site.
- Expecting the software to book inspections or send reminders. Notice to the municipality remains your responsibility.
How 4construct helps
- 4construct lets you keep stages, a daily diary and document references with one attached file each, all tied to the site, so inspection evidence stays organised.
- It does not manage document versions, handle signatures or certification, or notify the building department. Use your municipality process for bookings.
- Record each inspection the same way on every site, so a coordinator can compare how long stages wait for inspection across different municipalities and plan crews with fewer idle days.