Construction management Q&A
How do I keep holdback records on an Ontario job?
Short answer
- Create one site per project with the owner, street address, start and end dates and the declared budget in CAD, so every holdback figure you record belongs to a single, clearly named job.
- Add a budget category called Holdback and progress payments, then enter each payment or amount withheld as its own cost line with a date, a short description and the invoice number you used.
- Link each cost line to the stage it relates to, such as foundation or framing, so you can see later which stage a withheld amount came from and who the subcontractor was.
- Confirm costs once they are checked. Confirmed entries cannot be edited, so if an amount changes you cancel the line with a written reason and enter a corrected one instead of overwriting history.
- Before release dates, review the site report by category and compare your own notes with what your lawyer or accountant says is due, since the figures in 4construct are only what you typed in.
Regulations and references
- Ontario projects are governed by the Construction Act, R.S.O. 1990, c. C.30, which covers holdbacks, liens and prompt payment. Read the current consolidation on ontario.ca and ask a construction lawyer how it applies to your contract.
Practical example
- Example: a contractor renovating a detached house in Mississauga declares a budget of CAD 480,000. Each month she records the progress payment to the framer and a separate line for the amount held back, both dated and linked to the framing stage.
- Example: in Ottawa, a small builder has three subcontractors on one townhouse block. He enters a cost line per subcontractor per month, and at the end of the quarter he filters the Holdback category to see everything withheld on that site.
- Example: a small builder in London, Ontario finishes a duplex in two phases. He keeps one Holdback category per phase, enters every dated payment and every withheld amount, and prints the category report before his quarterly call with his bookkeeper to compare it with her own ledger.
Common mistakes
- Mixing the holdback amount into the gross payment line, which makes it impossible to see later how much was actually withheld from each subcontractor on a given month.
- Confirming a cost line before checking the amount against the invoice, then discovering it cannot be edited and having to cancel it with a reason.
- Treating the software figures as legal proof of what is owed instead of confirming release dates and amounts with a specialist and your signed contract.
How 4construct helps
- 4construct gives you dated, categorised cost records per site and stage, with confirmed entries locked and cancellations requiring a reason. That keeps your own holdback paper trail tidy.
- It does not calculate holdback, send payment reminders, register or discharge liens, or issue invoices. Those steps stay with you, your lawyer and your accountant.
- Keep your own notes about contract terms next to the figures, because the software cannot tell you when a holdback is due; that answer comes from your signed contract and professional advice.