Construction management Q&A
How do I track change orders against a CCDC contract budget?
Short answer
- Enter the original contract amount as the declared budget of the site in CAD, and split it into categories such as concrete, framing, mechanical, electrical and finishes, matching your schedule of values.
- For every change order or change directive, add a new budget line or category named with its number, for example CO-07 added pot lights, so the change never disappears inside an older line.
- Enter each cost that belongs to the change by hand, with a date, a description and the subcontractor, and link it to the stage where the work happens in the field.
- Confirm the costs once the invoices are checked. Confirmed costs are locked, and a cancellation needs a written reason, which gives you a clean audit trail for the owner conversation.
- Review the budget report by category at each progress meeting to compare the original lines with the change lines, using your own signed change documents as the authority.
Practical example
- Example: a general contractor builds a medical office in Halifax for CAD 2.4 million. Change order 03 adds a second hand-wash station at CAD 18,000. He creates a CO-03 budget line and enters the plumber invoices against it.
- Example: on a school addition near Edmonton, the owner directs extra work before the price is agreed. The contractor opens a line for the directive and enters costs as they occur, then updates the figures when the price is settled.
- Example: a renovation of a retail unit in Saskatoon sees four small owner requests in one month. The contractor numbers them CO-01 to CO-04 as budget lines, enters the electrician and drywall invoices against each, and brings a one-page category report to the site meeting.
Common mistakes
- Editing the original budget line to absorb each change, which hides how far the project has moved from the signed contract amount.
- Entering costs for a change under the original category, so the report cannot separate base scope from extras when the owner asks for a breakdown.
- Assuming 4construct produces change orders. It records your costs and budget, but the signed documents themselves must come from you and your consultant.
How 4construct helps
- 4construct holds the declared budget, budget lines by category and manually entered costs per site, with reports by site and category depending on your plan.
- It does not create change orders, approval workflows or progress certificates, and it does not value changes automatically. Those remain in your contract documents.
- Keep the signed change documents in your own contract file and attach a copy of any one as a document reference when it helps the team find it quickly on site.