How should I enter GST, HST and PST in my site costs?
Short answer
- Decide with your accountant whether each site records costs before or after sales tax, and write that rule in the site notes so everyone entering costs follows the same convention.
- Enter the amount exactly as your convention says, and mention in the description whether it includes GST, HST or PST, for example framing invoice 1042, before HST.
- Keep the currency as CAD on the site so every line is expressed the same way, even when a supplier in another province charges a different combination of taxes.
- If you split tax into its own line, use a dedicated category, for example Taxes paid, so that reports by category show materials and labour without tax mixed in.
- Check one month of entries against supplier invoices before confirming, because confirmed costs are locked and corrections need a cancellation with a written reason.
Practical example
- Example: a renovator in Vancouver buys CAD 10,000 of lumber and enters CAD 10,000 with the description before GST and PST. A second category tracks the tax separately so the budget compares like with like.
- Example: a builder in Moncton works under the harmonized tax and records invoices tax-inclusive. The site note states that rule in one sentence, which keeps the crew from entering a mix of both styles.
- Example: a contractor works on one site in Ontario and another in British Columbia. Each site note states its own entry convention, and the accountant can read both budgets without asking which lines include tax, because the description says it every time.
Common mistakes
- Mixing tax-inclusive and tax-exclusive amounts on the same site, which makes the budget report impossible to read at the end of the month.
- Assuming the software works out sales tax. 4construct records the numbers you type and does not calculate or file anything.
- Using the tax rules of another province without checking, then entering the wrong amount for a cross-border supplier invoice.
How 4construct helps
- 4construct stores costs you enter by hand with category, date and description, per site and stage, in the currency declared on the site.
- It does not calculate taxes, import supplier invoices or integrate with fiscal systems. Ask your accountant for the rules that apply to you.
- Review the convention at the start of every new site and write it once in the notes, since the cheapest correction is the one you never have to make later on. A short written rule in the site notes, shared with every person who enters costs, usually saves more time than any later clean-up of the figures.