Construction management Q&A
How do I allocate sparkies, plumbers and chippies in Perth?
Short answer
- List every trade business you use in Perth as a subcontractor, including the electrician, plumber, carpenter and tiler, so each has one record with the sites and stages they are working on.
- Allocate each subcontractor to a specific site and stage with its dates, for example electrical rough-in during frame, so you can see who is committed to which job in the same week.
- Check the allocation list before confirming a new start date, because two jobs asking for the same plumber on the same days is cheaper to fix on screen than on the footpath.
- Enter each trade confirmed cost under the correct budget category, so electrical, plumbing and carpentry totals are separate and you can judge each quote against what was actually spent.
- Note in the daily diary who turned up, how many people and what was finished, then compare that against the allocation to spot trades who regularly arrive late or leave early.
Practical example
- Example: a builder in Joondalup has a plumber booked for rough-in on two homes during the same week. On the allocation view the clash is clear, and the second job is moved by two days before anyone is stood down.
- Example: carpentry on a Subiaco renovation is budgeted at AUD 62,000. After frame, confirmed carpentry costs total AUD 41,000, and the category report shows the team still has AUD 21,000 for fit-out.
- Example: the diary on a Scarborough job records only two of four tilers on Monday. The supervisor adds a blockage note, and the allocation is used later to discuss crew numbers with the subcontractor.
Common mistakes
- Keeping trade bookings in a text thread, so nobody sees that the same crew has been promised to three sites during a single Monday morning.
- Combining all trade costs into one general line, which hides which trade is running over until the final account is already agreed.
- Treating the allocation as a roster. It records who is assigned where, but you still need to confirm availability with each trade directly.
How 4construct helps
- 4construct holds subcontractors, their allocations to sites and stages, and the budget lines and costs for each trade. It does not send booking reminders, track licences or equipment, or schedule crews automatically, so confirm each start with the trade yourself. Use it as the shared picture of who is committed where, and ring the trade to confirm anything that matters, because a screen cannot replace a conversation with a busy subcontractor.