How do I budget a remote Pilbara site with a crew?
Short answer
- Create the site with its remote address, the client and the dates, and state the currency explicitly as AUD, so a distant job is never mixed up with metro projects in your totals.
- Build budget lines for the costs that behave differently in the Pilbara, such as freight to Karratha or Port Hedland, camp or motel accommodation, travel, labour and materials.
- Record each cost manually once it is confirmed and put it against the line it belongs to, so a flight or a freight bill never disappears into a general overhead figure.
- Use the daily diary for crew numbers, who flew in or out, hours worked, heat or cyclone effects and deliveries that did not arrive, giving you a day-by-day account of remote conditions.
- Review the category report weekly while the crew is away, compare spending with each line, and speak to the client early if freight or accommodation is running above what you allowed.
Practical example
- Example: a contractor is building a small workshop near Karratha with a declared budget of AUD 520,000. Freight is allowed AUD 38,000 and accommodation AUD 64,000 as separate lines, so each can be watched.
- Example: a steel delivery is held up for four days by a cyclone warning. The diary notes the blockage, the crew on site and the standby hours, and a confirmed cost of AUD 5,200 for extra accommodation is entered.
- Example: after six weeks the category report shows labour on budget but travel at 85 percent of its line. The project manager changes the roster for the next fly-in and discusses the position with the client.
Common mistakes
- Hiding freight and accommodation inside a single material line, so a small change in the road transport rate quietly consumes margin before anyone sees it.
- Entering costs only after the crew returns, so the report you read mid-roster is already weeks behind the money that has actually been spent.
- Assuming the figures update on their own. Costs in 4construct are entered by your team, so someone must own the job of keeping them current. On a remote job that usually means naming one person in the site office, or at head office, who enters confirmed costs each week and checks them against the lines you set.