Short answer
- Write the outage into the daily diary as a blockage the same day, giving the approximate hours without power and which tools were affected, such as the cutting saw or the batching mixer.
- Add a budget category named for temporary power, then set a declared amount for generator hire, diesel and extension leads, so these costs stop hiding inside general site expenses.
- Enter each diesel purchase and generator hire invoice as a manual cost in rand with a short note of the date and site, and confirm it once the supplier’s slip checks out.
- If the outage pushes back a task, update the stage progress yourself and add a note in the diary, because nothing adjusts the stage automatically when power fails.
- At month end, filter your costs by that category on each site and decide whether the generator should be priced into quotes for future jobs in areas with long outages.
Practical example
- Example: a contractor fitting out shops in Rosebank records two outages of about two and a half hours each in a week. The diary shows the tile saw idle, and R3 200 of diesel and hire is entered under “Temporary power”.
- Example: a bricklaying team in Polokwane works by hand during an outage, so the diary records a reduced output of 180 bricks per person instead of the usual figure, which explains the slower wall stage.
- Example: a builder in Gqeberha hires a generator for R800 a day for a pour that cannot wait. He enters the cost separately, so the owner sees the reason for the extra spend instead of a vague “site costs” line.
Common mistakes
- Pricing the whole job as if the grid would always be on, then absorbing diesel and hire costs from profit without ever showing them as a separate line.
- Recording the outage in a text message to the foreman but not in the diary, so there is nothing dated to refer to when the owner asks about delays.
- Entering one lump sum for “generator stuff” at month end, instead of dated entries, which makes it hard to see which site really consumed the diesel.
How 4construct helps
- 4construct lets you note blocked hours in the diary and track diesel and hire as manual cost entries against a budget category. It does not read outage schedules, connect to generators or alert you in advance, so you decide when to plan around an outage.