How do I compare several jobsites as a Denver contractor?
Short answer
- Create each job as its own project with the owner, the address, the dates and the declared budget in dollars, so every site starts with the same basic information filled in.
- Use the same category names for budget lines across every project, such as framing, concrete, roofing and finishes, so reports can be compared without translating between naming styles.
- Enter costs as invoices are confirmed on each job and update stage progress by hand at least once a week, because the reports only show what your team has recorded.
- Open the report by project to see which jobs are drifting from their budgets, then open the report by category to see whether the same trade is a problem on several sites.
- Pick one day each week for a short review, and make notes of what to chase, so numbers move into decisions rather than staying on a screen.
Practical example
- Example: a builder in Denver runs five projects, from a $420,000 basement finish in Wash Park to a $3,800,000 infill in Highland. A single weekly look at the project report tells the owner where to spend time on Monday morning.
- Example: three of the five jobs show framing at over 90 percent of the line while only 60 percent of the work is done. That pattern across sites suggests a problem with one lumber supplier, not with the individual crews.
- Example: a remodeler in Aurora keeps the category names the same on every project. When the roofing line runs hot on two jobs, the office calls the roofing sub the same day and renegotiates before the next house.
Common mistakes
- Naming categories differently on each project. Reports will then show a dozen near-duplicate lines, and you lose the ability to compare one site against another.
- Looking at reports before costs are entered. Because nothing is automatic, a stale record gives false comfort, so agree on how soon after an invoice the cost must be logged.
- Reviewing only the total budget of each job. A project can look healthy overall while one category quietly runs out of room, so always check the category view too.
How 4construct helps
- The reports in 4construct summarize projects and categories from the budgets, costs and stage progress your team enters, and which reports you see depends on your plan.
- Reports cannot be exported, there are no live dashboards or automatic alerts, and the numbers are only as current as the entries. Use your accounting system for official job-cost records.