Construction management Q&A
How do I log hurricane delays on a Tampa jobsite?
Short answer
- Create one daily log entry per day for the project, including days when nothing happened, so a storm-related stoppage appears as a clear gap in work rather than a missing page.
- Write the weather in plain words, such as tropical storm warning, sustained wind, standing water or heavy rain, and note the time it began to affect the work.
- List the crew and subcontractors who actually showed up and the work they completed, with quantities where you have them, for example slabs poured or roof sheathing nailed off.
- Use the blockers field for what stopped the work, naming the trade and the area affected, such as roofing on the north building held back by wind.
- Update the affected phase manually. Mark progress as it really stands so the project shows the true state after the storm, then keep logging until the crew is fully back.
Practical example
- Example: a custom home in South Tampa has its roof dried-in on a Monday. A tropical storm warning on Wednesday stops all exterior work. The superintendent logs wind, the crew sent home at 10 a.m. and the blocked trades, and does the same on Thursday and Friday.
- Example: after the storm, a retail pad site in Brandon has two feet of standing water in the footing trenches. The log records the pump rental, the three laborers who cleared the site and the footing work that restarted on Tuesday, giving the owner a factual timeline.
- Example: a commercial roofer in Clearwater loses six working days over a month. Because every day has an entry, the contractor can sit down with the owner and show exactly which days had wind, which had rain and which were lost to cleanup.
Common mistakes
- Logging only the big storm day. Delay conversations are usually about the quiet days before and after, so skipping them leaves you with a story that has holes in it.
- Writing vague notes such as bad weather. Name the condition, the time and the trade stopped, because a specific entry is far more useful when the schedule is discussed later.
- Forgetting to move the phase progress afterwards. If the stage still shows the pre-storm percentage, anyone reading the report will think the site is further along than it is.