Construction management Q&A
How do I plan stages for a Wellington hillside build?
Short answer
- List the stages in the order the hill dictates, such as access and retaining, piles or poles, subfloor framing, floor, wall framing, roof, cladding and interior, and give each a planned start and finish.
- Allocate the specialist subcontractors to their stages, for example the pile driller, the crane operator and the framing crew, so the diary and the stage list show who was needed and when.
- Record wind, access and delivery constraints as blockages in the diary. On a steep Wellington section, a closed road or a gale can halt a crane lift for a whole day.
- Update stage progress by hand after each completed activity, and add the quantities, such as lengths of treated timber or number of poles installed, to the day entry.
- Review the stage list weekly against the planned dates and adjust the later stages manually, so the programme you show the owner reflects what really happened.
Practical example
- Example: a three-level house in Khandallah with a declared budget of NZ$1,900,000. The builder sets eight stages and notes that the crane day for the roof trusses must be rebooked after a southerly forces a lift to stop.
- Example: a retaining wall and driveway in Karori. The foreman logs 14 poles installed on one day and 9 on the next, with a blockage note for a narrow access road, and the stage moves from 20 to 55 per cent.
- Example: a renovation in Island Bay. The owner asks why the frame is later than planned, and the diary shows three windy days and a late timber delivery, each recorded on its own date.
Common mistakes
- Planning the stages as if the section were flat. Access, cranage and wind can dominate the timeline on hills.
- Forgetting to move later stages when an earlier one slips. Nothing reschedules itself, so the plan is only as good as your updates.
- Using the tool for crane or truck tracking. It does not follow equipment or vehicles; it records what you tell it.
How 4construct helps
- 4construct gives you stages with manual progress, subcontractor allocations, a daily diary with weather and blockages, and reports by site and category depending on your plan.
- It does not provide live monitoring, GPS or machine tracking, automatic alerts or an offline mode. It stays an organised record that you and your crew keep current.