Construction management Q&A
How do I record variations on a fixed-price contract?
Short answer
- Keep the original contract sum as the declared budget on the site, and do not overwrite it. That figure is the baseline every later change is measured against.
- Create a budget line category called Variations, or one per variation if you prefer, so extra work stays visibly separate from the original scope.
- When the client agrees a change, enter the cost manually as soon as it is incurred, with a description that names the instruction, the date and who asked for it.
- Confirm the entry once the figure is agreed. If an instruction is withdrawn or an amount is wrong, cancel the entry with a stated reason and enter the corrected figure.
- Reference the signed instruction or email as a document, one file per reference, and note the stage affected, so the paper and the cost can be found together.
Regulations and references
- NZS 3910 is a Standards New Zealand conditions of contract for building and civil engineering construction, and it deals with variations. Read the edition your contract actually uses, and ask a specialist if the wording is unclear.
Practical example
- Example: a house in Lower Hutt contracted at NZ$620,000. The owner adds a heated floor for NZ$9,500, which goes into the Variations category with the date and the email reference attached as a PDF.
- Example: a school classroom in Invercargill. A change to the window schedule adds NZ$3,800, and a later instruction removes part of it; the first entry is cancelled with a reason and a corrected one follows.
- Example: a café fit-out in Napier. The owner requests extra joinery late, the project manager records NZ$6,200, and the budget view shows the total moving from the original sum with a clear trail behind it.
Common mistakes
- Changing the declared budget each time something is added. You then lose sight of the original contract sum and cannot show how far it has moved.
- Recording variations from memory weeks later, when the date, the instruction and the amount are hard to prove.
- Expecting the tool to price the change or produce a claim. It stores the figures you type; it does not work from estimates or quantities.
How 4construct helps
- 4construct holds a declared budget, category lines, manual costs that cannot be edited once confirmed, and document references with one attachment each.
- It does not generate payment claims or valuations, run an approval workflow, or interpret your contract. Use it as an orderly ledger and take contract questions to a specialist.