Construction management Q&A
How do I stage an apartment block insulation project?
Short answer
- Treat the renovation of an apartment building (daudzdzīvokļu māja) as one site with a beneficiary, which is often the house association or its manager, and a clear address and date range.
- Break the work into stages such as scaffolding, facade insulation, roof, cellar ceiling, windows in common areas, staircases and finishing, and give each stage a short description.
- Update stage progress by hand each week after walking the facade with the foreman, because side elevations and gable walls rarely advance at the same pace.
- Open budget categories for materials, labour, scaffolding hire and design, and enter costs when confirmed, so the building manager can be told where the money has gone.
- Record the blockers in the journal, for example residents’ access, rain or an unexpectedly damaged wall, since these explain delays better than a single percentage.
Practical example
- Example: a five-storey Soviet-era block in Daugavpils, 60 apartments. The contractor sets six stages. After eight weeks, scaffolding and the south facade are done, and the manager reports 35 percent complete.
- Example: a project of EUR 480,000 in Rēzekne has a EUR 40,000 category for the roof. A hidden defect in the roof boards adds EUR 6,500, entered as a manual cost with a note, and the reserve is reduced.
- Example: in Jēkabpils two days are lost because tenants cannot move cars from under the scaffolding. The journal entry names the blocker and the date, and the next residents’ meeting gets a factual explanation.
Common mistakes
- Planning the renovation as a single block of work with no stages, so a delay on the gable wall cannot be separated from the progress on the rest of the facade.
- Letting progress percentages follow the calendar rather than the real state of the facade, which shows a comfortable picture until the final inspection proves it wrong.
- Not saving daily notes about access problems, which leaves the contractor without evidence when a housing association asks why the handover moved.