Construction management Q&A
How do I track foreign subcontractors on a site in Iceland?
Short answer
- Add each firm as a subcontractor with its full legal name, a contact person on site and the trade it covers, so that anyone on the team can identify who is who at the gate.
- Allocate the firm to the specific stages and the specific site where it works. A firm with workers on two sites in the capital area should appear in both allocations.
- Use the daily log to note how many people from each firm were on site, what they did and the quantities finished, so the numbers can be checked against invoices later.
- Attach one reference document per record, for example the signed subcontract as a PDF, and write in the title what it is. Keep the scan of the agreement where the whole team finds it.
- Enter the subcontractor’s costs under its own category, and compare them with the stage progress before each payment, using the report by category. Keep one person responsible for these checks on each site, so that the review happens every payment round and does not depend on who has time that week.
Practical example
- Example: a general contractor in Kópavogur hires an electrical crew of five from an outside firm for three months. The crew is allocated to installation stages on two buildings, and the daily log shows how many people were present each day.
- Example: a formwork subcontractor invoices 9.5 million ISK for the frame of an apartment block in Reykjavík. The site manager compares the invoice with the stage progress and the log of quantities before confirming the cost.
- Example: a PDF of the signed subcontract is saved as a document reference, with the date and trade in its title. When the foreman changes, the next person finds it in the site record in a minute.
Common mistakes
- Keeping subcontractor information in personal phones and email. When the site manager is away, nobody knows who is supposed to be on site.
- Assuming the number of people on site matches the invoice. Without a daily log of who was present, the only evidence is the subcontractor’s own claim.
- Mixing the subcontract with the main contract in one file. Name each document clearly, and keep every subcontract linked to its firm.
How 4construct helps
- 4construct stores subcontractors, their allocations per site and stage, daily team entries, costs and one attached file per document reference. It does not check work permits, tax status, social insurance or the legality of posted workers; seek advice from the relevant authority or a specialist.