What should a work manager write in the daily site log?
Short answer
- Write the date, the site and a short list of work done that day by area or floor, using the names your team already uses, so anyone can follow the entry without extra explanation, including a colleague who covers for the manager during a holiday week or a site visit by the owner.
- List the crew present, including the main contractor workers and each subcontractor, and note absences, because headcount is the first thing questioned when a delay is discussed later.
- Record measured quantities in metric units, for example square metres of plaster, cubic metres of concrete or tonnes of reinforcement steel, so they can be compared with supplier documents and costs.
- Add the weather in plain words and any blockage, such as missing materials, a closed access road or a pending decision from the owner, and say who must act next.
- Finish the entry before leaving the site and update stage progress by hand once a week, so the log and the progress figures remain consistent.
Practical example
- Example: a work manager in Rehovot writes for floor four that 210 square metres of plaster were finished by seven plasterers, that 3 tonnes of rebar arrived for floor five, and that a lift delay cost two hours.
- Example: at a hospital extension in Beer Sheva the manager notes a crew of fifteen, 60 cubic metres of concrete and a blockage because the electrical subcontractor did not arrive, and names the next call to make.
- Example: on a school site in Lod the owner asks why a corridor is late. The manager opens three entries showing a missing delivery of blocks, then enters the supplier invoice as a cost under structure, so the delay and its price sit side by side in the same site file for anyone who reviews the project later.
Common mistakes
- Writing the log at the end of the week from memory. Small details such as the number of workers and the exact blockage are lost quickly.
- Recording quantities in mixed units. Keep to metric units consistently so entries can be compared and totalled by anyone reading the history.
- Using the log as a private diary of complaints. Keep entries factual and specific, because the owner, partners or advisers may read them in a dispute.