Construction management Q&A
How do I manage subcontractors under a main contractor?
Short answer
- Add each subcontractor once, with the trade and contact details, for example reinforcement, plastering, aluminium windows or electrical work, so the same name is reused across all your sites.
- Allocate the subcontractor to the site and then to the stage they work on, such as structure, finishing or external works, so the office sees at a glance who is responsible for which part.
- Create a budget line per trade, for instance ILS 900,000 for aluminium and glazing, and enter each confirmed invoice from that subcontractor as a cost against the line.
- Use the daily log to note who was on site, the work done and the quantities, because disagreements about a missing day or a half-finished floor are easiest to settle with a dated entry.
- Keep the registration or licence copy of each subcontractor as a document reference with one file, and ask your legal adviser which proofs you must hold for the work in question.
Regulations and references
- The Registrar of Contractors operates under the Registration of Contractors for Construction Engineering Works Law, 1969, and only registered contractors may perform building engineering work within the limits set. Confirm the classification needed for your project with the Registrar.
Practical example
- Example: a main contractor in Ashdod runs a 40-unit project with eleven trades. Each subcontractor is allocated to the site and to a stage, and the office filters the list to see that the plasterers and the tilers both appear on stage three.
- Example: an aluminium subcontractor in Modiin has a budget line of ILS 650,000. After two confirmed invoices of ILS 200,000 each, the project manager sees ILS 250,000 left and can raise any additional request before it exceeds the line.
- Example: a contractor in Tel Aviv stores a copy of the registration certificate for each subcontractor as a single PDF reference, so the site manager can open it quickly during an inspection visit.
Common mistakes
- Keeping a subcontractor list in a spreadsheet separate from the site, so nobody knows which trade is allocated to which stage or whether the budget line has been created yet.
- Entering costs without the subcontractor name or the stage, which turns the cost list into an undifferentiated pile and makes the closing reconciliation slow.
- Assuming the software checks registration status. It stores your reference documents, but you or your adviser must verify each registration with the Registrar directly.
How 4construct helps
- The product records subcontractors, allocations to sites and stages, budget lines by category, manually entered costs and the daily log, with one file per document reference.
- It does not run an approval flow, check licences against any register, or send notifications to subcontractors, so verification and communication remain with your team.