How do I track deadlines and penalties in a construction contract?

Short answer

  1. Turn the contract dates into stages with start and end dates, not one single final deadline.
  2. Track the client's payment deadlines separately — penalties run both ways.
  3. Record every stoppage day and its cause in the site journal.
  4. Notify in writing any cause of delay that isn't yours, at the moment it arises.
  5. Calculate the penalty on actual days late, against the deadline as revised by addenda.

What the law says (brief)

  • Civil Code, Art. 1538 — a penalty clause is one where the parties fix in advance what the debtor owes on non-performance; the daily late-delivery percentage in construction contracts is a penalty clause.
  • Law 72/2013 on combating late payment — between professionals the statutory penalty interest is the National Bank reference rate plus 8 percentage points, and the payment term may not, as a rule, exceed 60 calendar days.
  • Law 50/1991 on authorising construction works — the declared execution period and the permit's validity are deadlines distinct from the contractual ones, but they are tracked together.
  • The construction acceptance regulation (Government Decision 273/1994, as amended by Government Decision 343/2017) — the date of acceptance at completion is the point the warranty period starts running from.

Practical examples

  • Example: an 850,000 RON contract carries 0.05% per day late. At 18 days late the penalty is 7,650 RON. Of those 18 days, 7 are rain days recorded in the journal and notified to the client, so the discussion is about 11 days, i.e. 4,675 RON.
  • Example: the client is 40 days late paying a 120,000 RON work statement. With no contractual clause, statutory penalty interest is calculated at the reference rate plus 8 percentage points for those 40 days.

Common mistakes

  • Tracking only the final deadline, so you learn about the slip when it can no longer be recovered.
  • Not notifying causes of delay outside your control in writing; when the penalty is computed, what was said verbally doesn't count.
  • Calculating the penalty against the original contract date, ignoring extensions granted by addenda.
  • Not tracking the client's payment deadlines, even though late-payment interest is something you can claim too.

How 4construct helps

  • Every stage has its own deadline, and the delay alert fires before the final deadline is missed.
  • Stoppage days and their causes stay dated in the daily journal, so the evidence exists when the penalty is discussed.
  • Stage progress is compared against the original plan, on every active site.
  • Progress reports sent to the client build a communication trail, useful when the deadline is renegotiated.
4b2b.net
Business Ecosystem
4conta.ro
Accounting
4invoices.net
Invoicing App
4expenses.net
Expense Management
4notify.net
Notifications
4hosting.net
Hosting
4database.net
Databases
4buildsite.net
Website Builder
4myapp.net
App Builder
4avatars.net
AI Avatars
4chaty.net
AI Chatbot
4webagency.net
Web Agency Software
4softedu.net
Education Websites
4softcrm.net
CRM Platform
4softerp.net
ERP System
4softhr.net
HR Management
4mystaff.net
Staff Portal
4construct.net
Construction Companies
4mycontracts.net
Contracts
4docs.net
Document Management
4appointments.net
Appointments
4marketingonline.net
Marketing
4insurance.net
Insurance
4property.net
Real Estate
4lawyers.net
Legal Software
4mygarage.net
Auto Service
4driving.net
Driving Schools
4fleet.net
Fleet Management
4myevents.net
Events
4therapy.net
Therapy
4clinics.net
Clinics
4dental.net
Dental Practices
4restaurants.net
Restaurants
4beautify.net
Beauty Salon
4gym.net
Fitness Gyms
4guards.net
Security Companies
4softvet.net
Veterinary Clinics
4softauto.net
Automotive Business Software
4marketplace.net
Marketplace
4shopy.net
Online Store
4pricing.net
Price Comparison
4salefood.net
Food Delivery
4rentify.net
Rentals
4transports.net
Transport
4agencytravel.net
Travel Agency
4hotel.net
Hotel Management
4ong.net
NGO Management