Construction management Q&A
How do I control materials on site so they don't go missing?
Short answer
- Receive every delivery on site and record the quantity actually unloaded, not the quantity ordered.
- Photograph the delivery and attach the photo to that day in the site journal.
- Allocate consumption to the stage the material was used on, not to the site in general.
- Periodically compare recorded consumption against the bill of quantities, on the expensive items.
- Investigate any gap larger than normal wastage while the crew is still on site.
What the law says (brief)
- Order 2634/2015 on financial and accounting documents — material receipts are evidenced by a delivery note or goods received note, and consumption by a material issue note.
- Accounting Law 82/1991 — material stocks are managed against documents and verified by stocktaking.
- Regulation (EU) No 305/2011 on construction products — materials incorporated into the works must carry a declaration of performance and CE marking, and their paperwork belongs in the construction technical logbook.
- Law 10/1995 on construction quality — using products without conformity documents leaves the contractor liable, regardless of who bought the material.
Practical examples
- Example: on a 12-apartment site the bill of quantities allows 1,290 m² of floor tiles plus 5% wastage, i.e. 1,355 m². Recorded consumption reaches 1,520 m². The 165 m² gap, at 70 RON/m², is 11,550 RON that never made it into the building.
- Example: a 24 t cement order is unloaded as 22.4 t weighed at the gate. Recorded that day, with a photo of the weighbridge ticket, the shortfall is settled with the supplier that month rather than at year-end stocktaking.
Common mistakes
- Signing for the material against the ordered quantity, without checking what was actually unloaded.
- Not allocating consumption to stages, so you can never say which piece of work overconsumed.
- Comparing consumption with the bill of quantities only at the end, when there is nobody left to ask.
- Leaving expensive materials — copper, tiles, joinery — without a daily record, on the assumption it will show up at the end anyway.
How 4construct helps
- Deliveries and consumption are logged in the daily journal, straight from site, with photos attached to the day.
- Material consumption feeds the project's materials cost centre automatically.
- The overrun alert on the materials cost centre fires during execution, not at final account.
- Consumption is visible per stage, so discrepancies surface at the stage that caused them.