Construction management Q&A

How do I verify the work quantities a subcontractor reports?

Short answer

  1. Compare the reported quantity against the contract bill of quantities, line by line.
  2. Have the quantity actually built measured on site, together with the technical inspector.
  3. Check the site journal to confirm the stage really was signed off on the days reported.
  4. Cross-check the matching material consumption — real blockwork square metres imply real blocks and mortar used.
  5. Approve the work statement only for the measured and confirmed quantity, not the requested one.

What the law says (brief)

  • Law 10/1995 on construction quality — execution must be documented, and the technical inspector checks the work against the verified technical design.
  • Fiscal Code, Art. 281(7) — for construction and assembly services the taxable event arises when the work statement is issued or, per the contract, when the client accepts it. Whatever you accept becomes payable.
  • Government Decision 907/2016 — for publicly funded projects, the bill of quantities and the cost estimate per work category are the benchmark reported quantities are measured against.
  • Accounting Law 82/1991 — costs are recorded against supporting documents, so a work statement must reflect quantities genuinely executed.

Practical examples

  • Example: the masonry subcontractor reports 480 m² for the ground floor, but the bill of quantities says 430 m². On-site measurement confirms 436 m² — the gap came from door and window openings not deducted. The statement is approved for 436 m²; at 55 RON/m² that avoids 2,420 RON.
  • Example: on electrical works, the 2,100 m of cable reported is compared with the routes in the design and with the delivery notes for cable received on site (1,850 m). The gap is settled before approval, not at final account.

Common mistakes

  • Approving a work statement on a declared progress percentage rather than measured quantities.
  • Not deducting openings — doors, windows, stairwells — from the reported areas.
  • Signing the statement without the technical inspector, then having no way to dispute the quantity at handover.
  • Checking quantities only at final account, once the subcontractor's crew has already left the site.

How 4construct helps

  • The contracted quantity per stage and per subcontractor sits next to the reported one in the Subcontractor Management module.
  • Work statements are generated from stages confirmed in the daily journal, not from what was reported verbally on site.
  • Photos stay attached to the day the stage was confirmed — the evidence stays in the project file.
  • The history per subcontractor shows how often reported quantities were corrected on verification.
4b2b.net
Business Ecosystem
4conta.ro
Accounting
4invoices.net
Invoicing App
4expenses.net
Expense Management
4notify.net
Notifications
4hosting.net
Hosting
4database.net
Databases
4buildsite.net
Website Builder
4myapp.net
App Builder
4avatars.net
AI Avatars
4chaty.net
AI Chatbot
4webagency.net
Web Agency Software
4softedu.net
Education Websites
4softcrm.net
CRM Platform
4softerp.net
ERP System
4softhr.net
HR Management
4mystaff.net
Staff Portal
4construct.net
Construction Companies
4mycontracts.net
Contracts
4docs.net
Document Management
4appointments.net
Appointments
4marketingonline.net
Marketing
4insurance.net
Insurance
4property.net
Real Estate
4lawyers.net
Legal Software
4mygarage.net
Auto Service
4driving.net
Driving Schools
4fleet.net
Fleet Management
4myevents.net
Events
4therapy.net
Therapy
4clinics.net
Clinics
4dental.net
Dental Practices
4restaurants.net
Restaurants
4beautify.net
Beauty Salon
4gym.net
Fitness Gyms
4guards.net
Security Companies
4softvet.net
Veterinary Clinics
4softauto.net
Automotive Business Software
4marketplace.net
Marketplace
4shopy.net
Online Store
4pricing.net
Price Comparison
4salefood.net
Food Delivery
4rentify.net
Rentals
4transports.net
Transport
4agencytravel.net
Travel Agency
4hotel.net
Hotel Management
4ong.net
NGO Management