Construction management Q&A
How do I log wet season delays on a Darwin site?
Short answer
- Write a diary entry every working day during the build-up and wet, noting the weather, the hours worked, the crew on site and which task was stopped or slowed by storms or standing water.
- Mark the cause plainly as a blockage, for example no concrete pour possible, site boggy, or crane stood down for wind, so delays can be found and counted later without re-reading every note.
- Update stage progress manually after each inspection so the numbers show how far the wet actually set you back, instead of relying on the original programme dates.
- Record extra costs such as pumping water, temporary protection or re-mobilising a subcontractor as confirmed costs against the right stage, with a clear description of why they arose.
- Pull a project report at month end and share the diary facts with the client or your adviser when discussing time, using wording that stays factual and avoids guessing about entitlements.
Practical example
- Example: a builder in Palmerston is framing a four-bedroom house for AUD 450,000 in January. The diary shows six lost days across three weeks, each with a short note on rainfall and which crew was sent home.
- Example: the concrete subcontractor returns twice because a pour was cancelled. The extra mobilisation of AUD 2,800 is entered as a confirmed cost against the slab stage, with the reason written in the description.
- Example: in April the supervisor compares the diary count with the planned handover. Seeing the lost days and the stage percentages together, the team resets expectations with the owner before the dry season rush.
Common mistakes
- Writing only the word rain in the diary, with no hours lost or task affected, which gives you nothing specific to point to when a delay is discussed.
- Letting each supervisor record delays in a private notebook, so the office sees the problem only when the schedule is already well behind.
- Assuming a delay automatically changes the contract date. Whether it does depends on your contract, so check it and speak to your adviser rather than rely on the diary alone.
How 4construct helps
- 4construct stores a daily diary with works, crew, quantities, weather and blockages, linked to your stages and confirmed costs for each site. It does not forecast weather, send storm warnings or calculate time extensions, so those decisions stay with you. The value is a clear, dated account of what happened on each wet day, kept next to the stage and the cost, which makes later conversations with owners and advisers calmer and better informed.