Construction management Q&A
How do I verify the work quantities a subcontractor reports?
Short answer
- Compare claimed quantities with the design, contract and measurements taken on site.
- Document discrepancies, units and the period checked; resolve them with the subcontractor before acceptance.
- Keep supporting documents separately. In 4construct you can record quantities in the journal and subcontractor assignments.
Practical examples
- Example: if a statement claims 90 m² and a measurement shows 85 m², record the 5 m² difference and agree the measured area before acceptance.
Common mistakes
- Do not compare quantities in different units without checking the measurement method.
How 4construct helps
- Record quantity and unit in the site journal and review the subcontractor assignment.
- Comparing measurements with contractual documents and accepting quantities remain separate tasks.