Construction management Q&A
How do I track variations on a fixed-price job in Adelaide?
Short answer
- Record the original fixed price as the declared project budget in AUD, then keep it unchanged, so every later variation is visible against the number the client first agreed to.
- Create a budget category for variations, or use the relevant trade category, and add a line for each requested change with a short description of what the client asked for.
- Attach the signed variation or email confirmation as a document reference with one file, so the paper trail sits next to the cost rather than in someone private inbox.
- Enter the cost of the variation work as confirmed costs on the correct stage once your trades have quoted or invoiced, and give any cancelled variation a written reason.
- Pull a project report before each progress discussion, showing original budget, variation lines and costs to date, so the conversation with the owner starts from the same facts.
Practical example
- Example: a builder in Norwood has a fixed-price renovation of AUD 290,000. The owner asks for a larger window in the living room and a variation line of AUD 6,400 is added with the signed email attached.
- Example: the same owner later changes their mind about the kitchen island. The earlier entry is cancelled with the reason written in full, and a new line of AUD 3,100 is recorded instead.
- Example: at lock-up the report shows the original price, AUD 9,500 of variations and AUD 211,000 spent so far. The builder uses it in a meeting at the Glenelg site office to agree the next step.
Common mistakes
- Agreeing variations on site by word of mouth and entering them weeks later, when the work is built and the owner remembers the price differently.
- Overwriting the original budget with the new total, which removes the evidence of how far the job has moved from the first agreed price.
- Treating the project record as the contract. Variation rules sit in your contract and local law, so check the process with a specialist before you rely on a note.
How 4construct helps
- 4construct keeps the declared budget, category lines, manually entered costs and one document reference file for each variation. It has no approval workflow and no quoting tool, and it does not produce variation notices or contracts. It simply keeps the original price, each change and its paper side by side, so the owner, the supervisor and the office can look at the same numbers before anyone commits to the next step.