How do I track base to fixing stages in Melbourne?
Short answer
- Create the Melbourne site and add four stages named base, frame, lock-up and fixing, then a handover stage, so the list matches the language your contract and clients already use.
- Set progress by hand after each inspection or supervisor walk, rather than guessing from calendar dates, and add a diary note explaining what was finished and what is still outstanding.
- Allocate subcontractors to the stage they work on, for instance the concreter on base and the carpenters on frame, so you can see who is committed where on any given week.
- Enter costs against the matching stage and budget category once confirmed, and use the category reports to compare spending on each stage with the budget you set for it.
- Attach the inspection sign-off or stage photo as a single document reference before you ask the client for the next progress payment, so the evidence sits next to the stage.
Regulations and references
- In Victoria, the Domestic Building Contracts Act 1995 deals with domestic building contracts, including staged progress payments. Consumer Affairs Victoria and the Building and Plumbing Commission publish guidance, so confirm current rules and any amendments before drafting your payment schedule.
- Victorian consumer guidance states that an owner appoints the relevant building surveyor, who carries out mandatory inspections but does not supervise the building work. Confirm your own inspection points with the appointed surveyor.
Practical example
- Example: a builder in Pakenham is putting up a single-storey home for AUD 380,000. The base stage is marked 100 percent after the slab inspection, with a photo of the surveyor sign-off attached as one document reference.
- Example: frame is at 70 percent. The diary notes that two framers from Dandenong are on site and that a roof truss delivery slipped by three days because of wind, which is recorded as a blockage.
- Example: the project manager compares frame costs of AUD 46,000 with a budget line of AUD 48,000. The difference is visible before the lock-up stage begins, while the supplier can still be spoken to.
Common mistakes
- Marking a stage complete before the inspection has actually passed, which makes the progress figure look better than the work and invites disagreement with the client.
- Using stage names that differ from the contract, so the office, the site team and the owner each talk about a different part of the build.
- Copying the Act into your own notes and treating it as current. Rules change, so read the latest official guidance and ask a specialist about your payment schedule.